![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Sky UK Ltd v Riverstone Managing Agency Ltd & Ors [2025] EWHC 1720 (Comm) (27 June 2025) URL: https://www.bailii.org/ew/cases/EWHC/Comm/2025/1720.html Cite as: [2025] EWHC 1720 (Comm) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT (KBD)
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
SITTING AS A JUDGE OF THE HIGH COURT
____________________
SKY UK LIMITED |
Claimant (705 Claim) |
|
MACE LIMITED - and – |
Claimant (536 Claim) |
|
(1) RIVERSTONE MANAGING AGENCY LIMITED (2) THE UNDERWRITING MEMBERS OF LLOYD'S SYNDICATE 3210 FOR THE 2014 YEAR OF ACCOUNT SUBSCRIBING TO POLICY B0509DD190814 (3) OLD COMPANY 18 LIMITED (4) ASPEN INSURANCE UK LIMITED (5) ROYAL & SUN ALLIANCE INSURANCE PLC (6) HSB ENGINEERING INSURANCE LIMITED (7) BERKSHIRE HATHAWAY INTERNATIONAL INSURANCE LIMITED (8) MSI CORPORATE CAPITAL LIMITED |
Defendants |
____________________
Paul Reed KC and Ebony Alleyne (instructed by Clyde & Co LLP) for the Claimant in the 536 Claim
John Lockey KC and Patrick Maxwell (instructed by DAC Beachcroft LLP) for the Defendants
Hearing dates: 27 June 2025
____________________
Crown Copyright ©
HH Judge Pelling KC:
Introduction
Background
"(2) The reasonable approach to rectifying insured damage as determined in accordance with (1) above; to include consideration of:
(a) whether any of the remedial schemes before the Court at trial represent a reasonable response to the insured damage;(b) whether it would be reasonable to incur the costs of 'lifting the lid' in order to determine how to remediate insured damage; and,(c) whether the remedial scheme found to be appropriate at paragraph 220 of the Trial Judgment should be adjusted to take account of any damage at upslope areas, plenums, insulation and soft spots.
(3) What (if any) further evidence is required to determine the quantum of damages."
It is submitted by the defendants that the hearing should be preceded by a sequence of written submissions addressing the stage 1 issues with the claimants going first followed by the defendants and then the claimants in reply. In principle I agree with the defendants firstly that there should be an oral hearing; secondly that it should be preceded by a sequence of written submissions in the order they propose and thirdly, I consider that any order should make clear that those written submissions should as far as possible be free-standing documents that set out comprehensively all the submissions that each of the parties wish to rely on with cross referencing only to the evidence relied on to support the findings sought.
a. These proceedings will be referred to NDR by facilitative mediation which is to be completed by no later than 18 August 2025; and if the dispute is not resolved then the following directions are to apply:
i. By 4pm 4 weeks before the hearing, Sky shall file and serve its written submissions relating to the Issues as defined below and Mace will file its written submission strictly limited to those Issues exclusively relevant to Mace's claim for an indemnity under the Policy;
ii. By 4pm 2 weeks before the hearing, the defendants shall file and serve their written submissions in answer to both Sky's and Mace's written submissions;
iii. By 4pm 1 week before the hearing, (a) the claimants shall file and serve their respective written submissions in reply to the defendants' submissions and (b) the parties will lodge an agreed bundle of authorities for use at the hearing;
iv. By no later than 7 days after the date of this Order the parties will apply to the Commercial Court Listing Office for a hearing of 3 days duration.
v. The issues ("Issues") to be addressed in the written submissions and the oral hearing are (1) the remaining issues of fact that have to be determined in order to give effect to the determination of the Court of Appeal that
1. damage after the end of the Period of Insurance was within the scope of the Policy and
2. Mace was entitled to be indemnified under the Policy not merely for the amount of damage at practical completion but for the cost of remedying the development and deterioration damage to which it gave rise; and
(2) the quantification of Sky's and Mace's claims
vi. No further evidence shall be admitted without further order.
However, I recognise that the parties have not had the opportunity to consider these directions and for that reason the parties are at liberty to submit brief written submissions as to the form of order to be adopted by no later than 4 pm three working days after receipt of this judgment in draft.